Wednesday 26 February 2014

KFC | Gainsborough | New Build





The Project

Appointed as Main Contractor by a UK leading KFC franchisee to construct another addition to the largest Quick Service Restaurant chain in the world - KFC, constructing a new KFC and Drive-Thru to an innovative design, in the heart of the redevelopment area of Gainsborough Town Centre

The site occupies the grounds and premise of the old Courthouse on Roseway, and Phase 1 of the works included the Demolition of the Old Courthouse which was a reinforced concrete structure. Phase 1 of the works (demolition) has already been completed by others

Phase 2 of Work involved the construction of a large single story retail unit which will now operate as a KFC with Drive thru. The building was constructed and the building process was managed by using modern methods of construction and it includes a steel frame with King span composite paneling, brick work and feature facetted glazed curtain wall cladding arrangements.
Due to previous demolition works on site foundations are driven concrete piles with reinforced ground beams. Works did also include making a new site entrance and both soft and hard landscaping to follow.
The project commenced August 2013 and was completed February 2014.

The Challenge

Overcoming made ground conditions and hidden RC Concrete underground obstructions as the works progress from the building to externals.

Ensuring the protection and safety of public at all times, as the site was bounded by pedestrian walkways.

Maintaining control of safe traffic management into and off site

Deep Drainage connections into areas of 4 way traffic.


'Finger Lickin Good'
Competition
As we have completed this project we are giving you the chance to win a free Family Feast Bucket. To enter simply follow the instruction on Facebook and Twitter.
                                     


Return to Pacy & Wheatley

Tuesday 11 February 2014

Healthcare Construction | Leeds


Project Large Image 510 x 330

1st Small Image 300 x 2502nd Small Image 300 x 250


The Project

Pacy and Wheatley Healthcare Construction project commenced on this prominent building that stood on a large raised site overlooking local amenities, consisted of an eight bed care facility with separate annex of two self contained units suitable for more able residents. The site backed on to beautiful woodland areas which were highlighted and open. The facility enjoyed lounge areas, kitchen dining room and specialist sensory area for relaxation. The terrace area was constructed to provide a peaceful retreat for residents to enjoy, complete with discrete systems to comply with the CSCI regulations. The front of the building was carefully landscaped around the large sloping car park with secure fencing to enclose the rear. The project is an OSC timber frame building clad with brick, render and art stone ensuring clean lines and pleasing aesthetics.

The Challenge

To produce a first class zero defects product for a valued client. Dealing with surface water run off from the higher forested ground to the rear. To complete the project on time and on budget. Battle with continued heavy snowfall throughout the build period. Ensure minimum disruption to local businesses and neighbours. Enable compliance with CSCI regulations and achieve an air test under 5.0.

The Solution

Utilise competent in house staff for the project who have a previous relationship with the client. Due to the inclement weather conditions, all efforts were put into getting as much groundworks completed at an early stage of the scheme. It was also imperative to ensure the timber frame was erected and sealed as soon as possible to ensure works could continue internally.

Key Achievements

Air permeability test achieved a very presentable 3.19. Arboriculture protection requirements were upheld fully on a very tight site. Our client was presented with a high standard of finish giving patients comfortable surroundings from the improved services. Working closely with flexible, local contractors to ensure the phased handovers were successfully completed.

Return to Pacy & Wheatley


Thursday 6 February 2014

Education Construction | Scunthorpe

Project Large Image 510 x 330

1st Small Image 300 x 2503rd Small Image 300 x 250

The Project

Pacy and Wheatley Educational Construction project was to create a conference and training facility to the first floor of an existing building. The work consisted of the demolition of a part completed scheme, the installation of new stud walls, ceilings, windows and lift to create office space, toilets, kitchen facilities and a room for training and conferences. In addition to internal work a number of remedial works we’re made to the externals improving the aesthetics of the building.

The Challenge

Working on a very constrained site with limited access for deliveries and parking.

Delivering the project with minimum disruption to neighbours, the general public and staff working on the ground floor.

Ensuring segregation of both the general public and staff from construction work.

Dealing with unforeseen structural problems with the building at the design stage.

The Solution

During the project, a number of chimney stacks we’re found to be unsafe and requiring further support. As the client’s budget was extremely tight, first rate communication between Pacy & Wheatley Construction and the structural engineers was required to achieve our goal within budget. To minimise disruption to neighbouring businesses deliveries were arranged at off peak times. This guaranteed efficient progress of the project, whilst ensuring the satisfaction of North Lincolnshire Homes’ neighbours.

To ensure the safety of both North Lincolnshire Home’s staff and the general public, fencing was erected to provide good segregation. Daily communication between Pacy & Wheatley and North Lincolnshire Homes throughout the project guaranteed the safety of all parties during our works.

Key Achievements

The project was delivered within an extremely tight budget, to the client’s full satisfaction.

Carried out with the minimum disruption to staff occupying the building throughout the duration of the project.

Excellent site management resulted in providing an outstanding finished product.

The successful installation of a lift within the constraints of the existing building.

Testimonials

Pacy and Wheatley Construction carried out the works in a professional manner and with minimal disturbance to the ground floor premises, which were occupied throughout the contract. Additional works that were required to deal with unforeseen structural issues were dealt with promptly and economically. The additional works required an extension of time which was amicably agreed and the project was completed on time and within budget.
Hugh Ashby, Architect, John Hill Associates.

Return to Pacy & Wheatley